Lee's Summit Road Lift Station EFHB

Lee's Summit Road Lift Station EFHB

Last Updated

07/20/2010

Project Category:

Water Utilities-Sewer

Project Contact:

Kevin York
816-969-1818

Estimated Construction Dates:

Feb 01, 2011 - Jun 01, 2011

Project Status

In Design

Projected Funding:

$150,000

Project Description:

This project involves rehabilitation of the excess flow holding basin at the Lee's Summit Road Lift Station. The initial project will be a study to recommend appropriate rehab measures. The project budget will be finalized once the study is complete.

Project Rationale:

The concrete-lined basin leaks and fills with groundwater, representing a source of I&I into the sanitary sewer system.

Status Details: