Cedar Creek Trunk-Winterset Woods & Sterling Hills
Cedar Creek Trunk-Winterset Woods & Sterling Hills
Last Updated
07/21/2010
Project Category:
Water Utilities-Sewer
Project Contact:
David Lohe
816-969-1814
Estimated Construction Dates:
Feb 01, 2014 - Aug 01, 2014
Project Status
Future
Projected Funding:
$565,000
Project Description:
This sanitary sewer improvement project consists of the construction of 2,600 LF of sanitary sewer relief lines ranging in pipe size from 12-inches to 15-inches in diameter on the lower segments of the Cedar Creek Interceptor Subbasins CC-03 and CC-04.
Project Rationale:
The existing lines do not have capacity to convey the predicted peak wet weather sanitary sewer flows nor meet the future needs of development. The condition of the existing pipe system is also a concern. There has been at least one documented overflow in these subbasins.