Harris Road Waterline Phase 1
Harris Road Waterline Phase 1
Last Updated
07/23/2010
Project Category:
Water Utilities-Water
Project Contact:
Donna Mosley
816-969-1809
Estimated Construction Dates:
Dec 13, 2010 - Aug 01, 2011
Project Status
In Design
Projected Funding:
$495,000
Project Description:
This project involves the replacement of existing 3" and 4" waterlines with a new 12" line. It is located along Harris Road from US 50 Highway to Herring Road within the Public Water Supply District #14 service area. This project will be bid in conjunction with the M150 & Doc Henry Water Replacement project.
Project Rationale:
Constructed in the mid-1960's, the waterlines in the area is under capacity for the current development. This is the last project to complete as part of PWSD#14. The district is dissolving and transferring all assets to the City of Lee's Summit.
Status Details:
Project is currently in the design phase and will bid fall 2010.



