Harris Road Waterline Phase 1

Harris Road Waterline Phase 1

Last Updated

07/23/2010

Project Category:

Water Utilities-Water

Project Contact:

Donna Mosley
816-969-1809

Estimated Construction Dates:

Dec 13, 2010 - Aug 01, 2011

Project Status

In Design

Projected Funding:

$495,000

Project Description:

This project involves the replacement of existing 3" and 4" waterlines with a new 12" line. It is located along Harris Road from US 50 Highway to Herring Road within the Public Water Supply District #14 service area. This project will be bid in conjunction with the M150 & Doc Henry Water Replacement project.

Project Rationale:

Constructed in the mid-1960's, the waterlines in the area is under capacity for the current development. This is the last project to complete as part of PWSD#14. The district is dissolving and transferring all assets to the City of Lee's Summit.

Status Details:

Project is currently in the design phase and will bid fall 2010.