Pryor Road and Summit Woods Traffic Signal
Pryor Road and Summit Woods Traffic Signal
Last Updated
08/04/2010
Project Category:
Bridges&Streets&Signals
Project Contact:
Jeff Wilke
816-969-1821
Estimated Construction Dates:
Aug 23, 2010 - Nov 29, 2010
Project Status
In Construction
Projected Funding:
$350,000
Project Description:
This project includes installation of a traffic signal on Pryor Road at the north driveway for the Summit Woods shopping center. The signal will be interconnected to the adjacent signals on Pryor Road.
Project Rationale:
Drivers are experiencing long delays as they wait to enter Pryor Road. With the opening of the new interchange, traffic volumes are expected to increase on Pryor Road to the point where the traffic signal will be warranted in the near future.
Status Details:
Construction will begin later this summer. The timing of this project is such that the signal will be in operation before the Holiday shopping season.