Pryor Road and Summit Woods Traffic Signal

Pryor Road and Summit Woods Traffic Signal

Last Updated

08/04/2010

Project Category:

Bridges&Streets&Signals

Project Contact:

Jeff Wilke
816-969-1821

Estimated Construction Dates:

Aug 23, 2010 - Nov 29, 2010

Project Status

In Construction

Projected Funding:

$350,000

Project Description:

This project includes installation of a traffic signal on Pryor Road at the north driveway for the Summit Woods shopping center. The signal will be interconnected to the adjacent signals on Pryor Road.

Project Rationale:

Drivers are experiencing long delays as they wait to enter Pryor Road. With the opening of the new interchange, traffic volumes are expected to increase on Pryor Road to the point where the traffic signal will be warranted in the near future.

Status Details:

Construction will begin later this summer. The timing of this project is such that the signal will be in operation before the Holiday shopping season.