Colbern Road Traffic Signal at Campbell Middle Sch
Colbern Road Traffic Signal at Campbell Middle Sch
Last Updated
08/11/2010
Project Category:
Bridges&Streets&Signals
Project Contact:
Jeff Wilke
816-969-1821
Estimated Construction Dates:
Jun 01, 2011 - Aug 15, 2011
Project Status
In Design
Projected Funding:
$290,000
Project Description:
A traffic signal will be installed on Colbern Road at the intersection with the main driveway to Campbell Middle School.
Project Rationale:
A school traffic study identified the need for a traffic signal at this location.
Status Details:
This project is currently being designed by City Staff. The traffic signal will be constructed during Summer 2011.



