Colbern Road Traffic Signal at Campbell Middle Sch

Colbern Road Traffic Signal at Campbell Middle Sch

Last Updated

08/11/2010

Project Category:

Bridges&Streets&Signals

Project Contact:

Jeff Wilke
816-969-1821

Estimated Construction Dates:

Jun 01, 2011 - Aug 15, 2011

Project Status

In Design

Projected Funding:

$290,000

Project Description:

A traffic signal will be installed on Colbern Road at the intersection with the main driveway to Campbell Middle School.

Project Rationale:

A school traffic study identified the need for a traffic signal at this location.

Status Details:

This project is currently being designed by City Staff. The traffic signal will be constructed during Summer 2011.