Sampson Road Safety Improvment

Sampson Road Safety Improvment

Last Updated

08/16/2010

Project Category:

Bridges&Streets&Signals

Project Contact:

George Binger
816-969-1828

Estimated Construction Dates:

Aug 07, 2010 - Sep 06, 2010

Project Status

In Construction

Projected Funding:

$500,000

Project Description:

This project will straighten the S-curve located south of the bridge over Mouse Creek and north of Hook Road. The road will be widened to approximately 20-feet with shoulders. The length of road work will be about 500 feet. The road will be closed during construction.

Project Rationale:

This project is a safety improvement. The existing curve is blind, the road is very narrow and the ditches are very steep.

Status Details:

The project has been bid. A Council packet has been completed and awarded to Summit Construction. A preconstruction meeting was August 11, 2010. Sampson Road will be closed starting September 7, 2010 and estimated to be opened again in Mid October.

Southbound Approach