Sampson Road Safety Improvment
Sampson Road Safety Improvment
Last Updated
08/16/2010
Project Category:
Bridges&Streets&Signals
Project Contact:
George Binger
816-969-1828
Estimated Construction Dates:
Aug 07, 2010 - Sep 06, 2010
Project Status
In Construction
Projected Funding:
$500,000
Project Description:
This project will straighten the S-curve located south of the bridge over Mouse Creek and north of Hook Road. The road will be widened to approximately 20-feet with shoulders. The length of road work will be about 500 feet. The road will be closed during construction.
Project Rationale:
This project is a safety improvement. The existing curve is blind, the road is very narrow and the ditches are very steep.
Status Details:
The project has been bid. A Council packet has been completed and awarded to Summit Construction. A preconstruction meeting was August 11, 2010. Sampson Road will be closed starting September 7, 2010 and estimated to be opened again in Mid October.