Bayview Drive Water- Channel Dr to Shore Line Dr
Bayview Drive Water- Channel Dr to Shore Line Dr
Last Updated
07/23/2010
Project Category:
Water Utilities-Water
Project Contact:
Donna Mosley
816-969-1809
Estimated Construction Dates:
Jul 13, 2011 - Oct 13, 2011
Project Status
Future
Projected Funding:
$656,000
Project Description:
Relocation of approximately 2,300 linear feet of 6-inch water main and service connections along Bayview Drive from Channel Dr to Shore Line Drive. The line will be relocated into the existing roadway due to the numerous obstructions along the existing alignment.
Project Rationale:
The existing line is deep and located under retaining walls, sidewalks and landscaping features, which results in high maintenance costs when repairs are needed. The main has experienced several breaks.