Middle Big Creek - Mouse Creek Flow Holding Basin
Middle Big Creek - Mouse Creek Flow Holding Basin
Last Updated
07/20/2010
Project Category:
Water Utilities-Sewer
Project Contact:
Ray Seidelman
816-969-1851
Estimated Construction Dates:
Aug 01, 2009 - Sep 04, 2010
Project Status
In Construction
Projected Funding:
$6,213,000
Project Description:
This project is the design of an excess flow-holding basin, a pump station structure, a force main, and two (2) gravity sewer lines in the vicinity southwest of the intersection of Ward Road and M-150 Highway. The basin and sewer will serve existing and new development in the area including the Stoney Creek, Parkwood, Meadows of Summit Ridge and Arbor Walk subdivisions.
Project Rationale:
The basin is needed to handle peak wet weather flows that exceed the capacity of the existing Little Blue Valley Sewer District line under Raintree Lake.
Status Details:
The contractor has completed all of the underground structures. The electrical building needs the roof installed. Restoration behind the homes will begin this fall.