Directions:

Obtain project details by selecting the desired project on the map, or review a list of unmapped projects from the link above.


Lee's Summit, MO

Airport Land Acquisition

Last Updated

08/18/2009

Project Manager(s):

John Barker
816-969-1850

Estimated Construction Dates:

Jun 01, 2005 - Jun 30, 2010

Project Status

N/A

Projected Funding:

$18,200,000

Project Description:

This project involves the purchase of properties adjacent to the Lee's Summit Municipal Airport as shown on the Airport Layout Plan approved in March 2000.

Project Rationale:

This land acquisition is required in order to provide Runway Protection Zones RPZ's)for the extension of Runway 18/36; to provide RPZ's for both ends of Runway 11-29; and to provide development area for the construction of a new terminal and new hangars to replace the existing hangars that will be demolished to meet FAA airport design standards.

Current Project Status:

The process of land acquisition includes surveys, appraisals, Environmental Site Assessments, and negotiations. The process is underway for all of the properties involved. The City has acquired thirteen of the tracts and has one offer pending.

The surveyor and appraiser have completed all of the surveys and appraisals for the remaining tracts.

The land acquisition program for the airport is on hold pending the outcome of the Airport Business Plan.


Airport Preliminary Engineering

Last Updated

08/18/2009

Project Manager(s):

John Barker
816-969-1850

Estimated Construction Dates:

Apr 01, 2004 - Sep 30, 2007

Project Status

N/A

Projected Funding:

$577,000

Project Description:

This project includes thirty percent engineering design, drawings, and estimates for the development of the airport as depicted in the Master Plan adopted in March, 2000.

Project Rationale:

This project is needed in order to provide engineered design and estimates to verify previous cost estimates.

Current Project Status:

Crawford Murphy and Tilley is the consultant and has submitted the drawings and report to finalize the 30 percent engineering.


Bailey Road, Route 291 to Hamblen Rd

Last Updated

01/29/2010

Project Manager(s):

Scott Ward
816-969-1849

Estimated Construction Dates:

Jun 01, 2011 - Dec 31, 2012

Project Status

In Design

Projected Funding:

$8,389,000

Project Description:

This project is one of six in the Lee's Summit Thoroughfare Master Plan. Funding for this project comes from the extension of the 1/2 cent sales tax (for Transportation Improvements) passed by voters in the spring of 2007. The project will construct a new roadway from M-291 east to the intersection of Hamblen Road and Bailey Road. A significant part of the project will be the design and construction of a bridge over the Union Pacific Railroad.

Project Rationale:

Current Project Status:

The concept / study phase is complete. The award of the contract, for the remaining design services, occurred in January 2010. Design work will begin in February 2010. Design, permitting and property acquisition is expected to take between 12 months and 18 months.


Bayview Drive Water- Channel Dr to Shore Line Dr

Last Updated

07/28/2009

Project Manager(s):

David Lohe
816-969-1814

Estimated Construction Dates:

-

Project Status

Future

Projected Funding:

$310,000

Project Description:

Installation of 2,200 linear feet of a new (relocated) 8-inch water main and service connections along Bayview Drive from Channel Dr to Shore Line Drive.

Project Rationale:

The existing line is deep and located under retaining walls, sidewalks and landscaping features, which results in high maintenance costs when repairs are needed. The main has experienced several breaks.

Current Project Status:


Blackwell Interchange at 50 HWY

Last Updated

07/28/2009

Project Manager(s):

Michael Park
816-969-1820

Estimated Construction Dates:

Apr 01, 2014 -

Project Status

In Design

Projected Funding:

$23,000,000

Project Description:

Extension of Blackwell Road across 50 Highway, having a diamond interchange. Construction of Blue Parkway to Blackwell Road and Oldham Parkway to Smart Road, with an intersection at Blackwell Road. This project will be fully funded by the East 50 HWY TIF and managed by the City of Lee's Summit. MoDOT, City of Lake Lottawanna and Jackson County are supporting agencies with property interests and/or ownership.

Project Rationale:

Traffic conditions at the interchange of Todd George Parkway and 50 Highway will not accomodate the immediate and projected growth of surrounding development. Improvements to Todd George Parkway interchange are planned, but cannot mitigate the traffic congestion without alternate access to 50 Highway in eastern Lee's Summit. Blackwell interchange has been planned for over 40 years. Blackwell interchange will relieve some of the congestion at Todd George Parkway and surrounding streets, provide better access to eastern Lee's Summit, minimize the impact of travel during construction at Todd George Interchange, encourage economic development in the newly annexed property and meet the City's long range traffic demand.

Current Project Status:

TranSystems was selected as the design firm, teamed with HDR. Design is approximately 85% complete. The interchange has been designed with roundabout traffic control where the ramps intersect with Blackwell Road and at the intersection of Blackwell Road and Blue Parkway/Shenandoah Drive. All permits and enviornmental clearances have been approved. Design will be completed, but acquisition of right-of-way and construction will be deferred until TIF funds are available to cover project costs.


Blackwell Road: Langsford Road to South Park Prop

Last Updated

01/29/2010

Project Manager(s):

Bob Netterville
816-969-1813

Estimated Construction Dates:

Mar 03, 2009 - Oct 31, 2009

Project Status

In Construction

Projected Funding:

$3,599,000

Project Description:

This project involves the reconstruction of Blackwell from the south edge of Legacy Park to just south of Langsford Road as a three-lane undivided roadway, curbs and gutters, sidewalks, and drainage structures. The project also includes reconstruction of the intersection at Blackwell and Langsford which includes the installation of a traffic signal. The project is partially funded by Jackson County since a portion of the road is in the county.

Project Rationale:

Blackwell Road will be a major north- south corridor on the east side of the City. The projected increase in traffic in this area due to development and the new park warrant the need for improvements. This project is part of the 1997 Road Sales and Excise Tax program.

Current Project Status:

The project was open for traffic December 4, 2009. Minor work remains; small areas fo sidewalks, grading and sod, and restoration of temporary church access area.


Browning Avenue Water- SE 5th to SE 7th

Last Updated

10/02/2009

Project Manager(s):

Ray Seidelman
816-969-1851

Estimated Construction Dates:

Jul 17, 2009 - Oct 27, 2009

Project Status

In Construction

Projected Funding:

$251,000

Project Description:

This rehabilitation project includes the replacement of 1,000' of 2-inch galvanized and 4-inch cast iron water lines with 8-inch pipe between 5th and 6th street and 6-inch pipe between 6th and 7th street.

Project Rationale:

The existing lines are substandard in size, and there are no fire hydrants along the line.

Current Project Status:

The project is complete.


CC Watershed - CC-16, CC- 20 Private I/I Rehab

Last Updated

11/03/2009

Project Manager(s):

David Lohe
816-969-1814

Estimated Construction Dates:

Oct 01, 2010 - Oct 31, 2011

Project Status

In Construction

Projected Funding:

$584,000

Project Description:

This sanitary sewer improvement project consists of completing the private I/I rehabiliation work identified in the Sewer System Evaluation Survey(SSES) in the identified sub-watersheds CC-16 and CC-20. These improvements consist of removal of ground water infiltration and inflow from home drain systems.

Project Rationale:

This project will serve existing customers by reducing I/I from these sources which will alleviate sanitary sewer overflows and backups in homes.

Current Project Status:

An intial 12 properties wiht I/I defects have been identifed by the Enigneer and City staff, and will be involved in the City's Cedar Creek CC-16 abd CC-20 Watershed Sub-basin Backup Prevention Program.


CC Watershed - CC-17, CC- 21 Private I/I Rehab

Last Updated

11/03/2009

Project Manager(s):

David Lohe
816-969-1814

Estimated Construction Dates:

-

Project Status

Future

Projected Funding:

$500,000

Project Description:

This sanitary sewer improvement project consists of completing the private I/I rehabiliation work identified in the Sewer System Evaluation Survey (SSES) in the identified sub-watersheds CC-17 and CC-21. These improvements consist of removal of ground water infiltration and inflow from home drain systems.

Project Rationale:

This project will serve existing customers by reducing I/I from these sources which will alleviate sanitary sewer overflows and backups in homes.

Current Project Status:


Cedar Creek Interceptor - Segments 1, 2-1

Last Updated

11/03/2009

Project Manager(s):

Kevin York
816-969-1818

Estimated Construction Dates:

Mar 09, 2010 - Nov 01, 2010

Project Status

In Design

Projected Funding:

$3,376,000

Project Description:

Segment 1 consists of replacing and upsizing approximately 9,481 lineal feet of sanitary sewer pipe ranging in size from 30-inch to 54-inch in diameter. This project is located in the Cedar Creek watershed between and including manhole 20-001 to manhole 28-276. Segment 2-1 consists of replacing and upsizing approximately 1,230 lineal feet of sanitary sewer pipe ranging in size from 30-inch to 36- inch in diameter. This project is located in the Cedar Creek watershed and including manhole 28- 276 to manhole 28-044. Segment 2-1 connects with Segment 1 at manhole 28-276.

Project Rationale:

The interceptor segments 1 and 2-1 have been identified in the Wastewater Master Plan (June 2007) as being undersized for the inability to convey predicted peak wet weather flows and not meet the future needs of development. The condition of the existing pipe system is a concern. Current flow monitoring of this sanitary sewer alignment indicated condition issues with this particular line.

Current Project Status:

Final design for this project is finishing up this winter. Easement acquistions and advertisement of the project is expected to be completed by early 2010.


Cedar Creek Sewer - Winterset & Sterling Hills

Last Updated

11/03/2009

Project Manager(s):

David Lohe
816-969-1814

Estimated Construction Dates:

-

Project Status

Future

Projected Funding:

$565,000

Project Description:

This sanitary sewer improvement project consists of the construction of 2,600 LF of sanitary sewer relief lines ranging in pipe size from 12-inches to 15-inches in diameter on the lower segments of the Cedar Creek Interceptor Subbasins CC-03 and CC-04.

Project Rationale:

The existing lines do not have capacity to convey the predicted peak wet weather sanitary sewer flows nor meet the future needs of development. The condition of the existing pipe system is also a concern. There has been at least one documented overflow in these subbasins.

Current Project Status:


Chipman Road Bridge over Cedar Creek

Last Updated

01/29/2010

Project Manager(s):

George Binger
816-969-1828

Estimated Construction Dates:

May 01, 2010 - Sep 30, 2009

Project Status

In Design

Projected Funding:

$1,869,000

Project Description:

This project is the replacement of the existing Chipman Road Bridge over Cedar Creek, just west of the RR overpass. The existing bridge shall be removed with a new bridge constructed in the same location. A signal will be installed for traffic safety through the tunnel under the old railroad embankment. Chipman Road will be closed in this area for during the construction phase of the project.

Project Rationale:

The existing bridge is a deteriorating concrete structure with a 10-ton load limit. The heaviest traffic the bridge can now support is a school bus. If not replaced, other action will would be taken within the next year to either lower the posted load limit (no school buses), reduce to one lane lane of traffic, and/or reduced speed limit over the bridge or closing the bridge.

Current Project Status:

Right of way and easement acquistion is completed for this project. Final plans have been completed and will be advertised for Construction on February 5th. Construction should start around May 1st. Chipman Road will be closed during construction for approximately 4 months. Traffic will be detoured to 3rd Street, View High and/or the new Pryor Road interchange.


Chipman Road, View High Dr to Bent Tree Dr

Last Updated

01/29/2010

Project Manager(s):

John Barker
816-969-1850

Estimated Construction Dates:

Jun 01, 2011 - Jun 30, 2012

Project Status

In Design

Projected Funding:

$11,777,000

Project Description:

This project is one of six projects funded by the 2007 1/2 cent sales tax renewal. This project will reconstruct the roadway as a 3-lane facility and acquire right-of-way for ultimate divided 4-lane facility with turn lanes. The existing one-lane RR tunnel will be removed, and widened to support two-way traffic.

Project Rationale:

SAFETY: This project will improve safety by leveling the roadway and improving sight distance. The right of way component will preserve right of way for future capacity improvements.

Current Project Status:

Project scoping and concept development have begun. Selection of a design consultant will begin in February, with design work commencing around April of this year.


Chipman Road: M-291 Hwy. to Birchwood

Last Updated

12/01/2009

Project Manager(s):

John Barker
816-969-1850

Estimated Construction Dates:

-

Project Status

In Design

Projected Funding:

$3,867,000

Project Description:

This project involves the construction of a new residential collector road from M-291 Highway to Birchwood Drive including a bridge. The total length of the roadway is approximately 3,500 feet. The project includes new sidewalk, curb and gutter, and storm drainage inprovements.

Project Rationale:

This road will be an east-west route for residential traffic to and from the Foxwood and Bordner subdivisions. This project is part of the 1997 Road Sales and Excise Tax program.

Current Project Status:

The Request for Qualifications was issued and Delich Roth and Goodwillie (DRG) was selected to perform the design. The City awarded DRG the design and they began work in April, 2008. The scope of the concept phase was to look at alternative layouts to determine which will be the most efficient and cost effective. A public meeting was held in December, 2008 and comments received from the residents. A draft of the Concept Phase Report is completed. When Concept is finalized, Preliminary Design will begin. The concept phase is complete.

The design of this project will stop at this point until further direction is received from City Council. Construction will be delayed indefinitely.


Colbern Road Street Lighting

Last Updated

01/20/2010

Project Manager(s):

Jeff Wilke
816-969-1821

Estimated Construction Dates:

Nov 02, 2009 - Apr 02, 2010

Project Status

In Construction

Projected Funding:

$583,000

Project Description:

This project includes installation of a continuous street light system on Colbern Road from Todd George Parkway to the east city limit.

Project Rationale:

Lighting on arterial roadways is currently not part of the leased system. Safety is a concern for the driving public. Studies have shown that streets with continuous street lighting have a lower crash frequency at night than streets without lighting.

Current Project Status:

Construction of underground equipment (pole bases and power supply foundations) was completed December 4, 2009.


Douglas St Water - 7th Street to 9th Street

Last Updated

11/16/2009

Project Manager(s):

Ray Seidelman
816-969-1851

Estimated Construction Dates:

Aug 12, 2009 - Sep 21, 2009

Project Status

In Construction

Projected Funding:

$322,000

Project Description:

This project involves the replacement of 1,120 feet of existing water main along Douglas Street between 7th Street and 9th Street. Temporary water mains are planned to supply customers with water service during construction.

Project Rationale:

This main has been repaired numerous times. The soils in the area are very corrosive and a non- ferous pipe and pipe bursting construction methods are being considered.

Current Project Status:

The project is completed.


Douglas Street Median and Lighting Improvements

Last Updated

01/20/2010

Project Manager(s):

Jeff Wilke
816-969-1821

Estimated Construction Dates:

Jul 19, 2010 - Feb 28, 2011

Project Status

In Design

Projected Funding:

$1,010,000

Project Description:

This project includes the addition of a median on Douglas between Vicotria and Tudor, a southbound right-turn lane at Victoria and associated signal relocations and modifications at the intersections to accomodate U-turn traffic. Continuous street lighting will also be installed along Douglas Street between Chipman Road and I-470.

Project Rationale:

The improvements will control unsignalized vehicle movements to improve safety and roadway capacity as the traffic volumes along this major corridor continue to increase.

Current Project Status:

This project is currently being designed. A public meeting was held at Lee's Summit City Hall on Tuesday, December 8, 2009. A webpage for the project has also been created to provide information about the project, and to recieve more public comments. Please visit http://cityofls.net/Transportation/Traffic/Douglas-Street-Improvements.aspx


East Prairie Lee Excess Flow Holding Basin

Last Updated

12/10/2009

Project Manager(s):

Ray Seidelman
816-969-1851

Estimated Construction Dates:

Sep 15, 2009 - May 01, 2010

Project Status

In Construction

Projected Funding:

$1,200,000

Project Description:

Approximately 1.8 MG of storage for peak wet weather flows from the East Prairie Watershed (EPL). Phase 1 of this project will serve the existing Summit Mill subdivision as well as the Woods property that has been annexed into the City. The Excess Flow Holding Basin (EFHB) is required for development of Woods property and the EPL watershed. This project is fully funded by the Sewer Tap Fee. The developer of the annexed property will reimburse the City for a portion of the costs in accordance with the pre- annexation agreement.

Project Rationale:

This basin will serve exsiting and future customers by reducing peak wet weather flows to downstream sewers and reducing overflows.

Current Project Status:

The Basin work has been suspended until excess material issues are resolved. The access road work has been suspended due to cold weather


East Terminal Area - LXT

Last Updated

11/30/2009

Project Manager(s):

John Barker
816-969-1850

Estimated Construction Dates:

Jun 03, 2008 - Sep 15, 2009

Project Status

In Construction

Projected Funding:

$6,500,000

Project Description:

This Project began on June 3, 2008. The project consists of the development of a new parallel taxiway on the East side of the Airport and an aircraft parking apron area. Also included are installation of wildlife fencing, clearing of obstructions in the runway protection area, and the remarking of both runways. The work was performed by Emery Sapp & Sons.

Project Rationale:

The Masterplan for the airport includes upgrading the airport to a C-II airport. The west parallel taxiway is too close to the north-south runway (R/W 18-36) to meet the C-II standards. A new terminal area needs to be developed on the east side of R/W 18-36 before the existing terminal and some hangars can be removed, allowing the relocation of the west parallel taxiway.

Current Project Status:

With the exception of final seeding in some areas, this project is complete.


Hook Road: Ward Rd to Route 291

Last Updated

01/29/2010

Project Manager(s):

Bob Netterville
816-969-1813

Estimated Construction Dates:

-

Project Status

Future

Projected Funding:

$7,908,000

Project Description:

This project will widen and reconstruct Hook Road as a 3-lane facility from Ward Road to Hwy. 291.

Project Rationale:

This project is one of six projects funded by the 2007 1/2 cent sales tax. Priority #6.

Current Project Status:

Project design and concept development will start in 2010 and performed in-house by City staff.


Hwy M-150 Water - Hwy M-291 to Doc Henry Road

Last Updated

11/12/2009

Project Manager(s):

Donna Mosley
816-969-1809

Estimated Construction Dates:

Aug 15, 2010 - Dec 16, 2011

Project Status

In Design

Projected Funding:

$396,000

Project Description:

The original project scope involves the replacement of 2,600 feet of the existing 16" with a 12" water main along M150 Highway from 291 Highway to Doc Henry Road. The scope was expanded to include the replacement of 1,100 feet of the 12" water from M150 Highway along Doc Henry Road. In addition, this project will include the design of an additional 1,500 feet along Doc Henry Road; however, actual replacement of this segment of 12" water line will be subject to availability of funds.

Project Rationale:

The existing water main has been repaired numerous times. Soils in the area are corrosive so HDPE or PVC pipe materials are being considered for the project.

Current Project Status:

Project is in the preliminary design phase which includes collecting survey data and information.


Jefferson Street Water - Market to Stuart Road

Last Updated

07/28/2009

Project Manager(s):

Carl Brooks
816-969-1847

Estimated Construction Dates:

-

Project Status

Future

Project Description:

This rehabilitation project includes the replacement of existing 2-inch galvanized and 4-inch cast-iron water lines with new 8-inch diameter ductile iron lines along Jefferson. The project is funded by the Water Construction fund.

Project Rationale:

The existing lines have a long maintenance history of numerous repairs.

Current Project Status:

This is a future project.


Jefferson Street, Persels Rd to Stuart Rd

Last Updated

01/29/2010

Project Manager(s):

Bob Netterville
816-969-1813

Estimated Construction Dates:

-

Project Status

Future

Project Description:

This project is one of six projects funded by the 1/2 cent sales tax, approved in 2007. Priority #2. Widen and reconstruct as a 2-lane facility with turn lanes.

Project Rationale:

Current Project Status:

Project design will be done in-house. Conceptual design will start in early January, 2010.


KC Water Supply Proposal - Phase III

Last Updated

12/22/2009

Project Manager(s):

Ray Seidelman
816-969-1851

Estimated Construction Dates:

-

Project Status

In Construction

Projected Funding:

$7,867,000

Project Description:

Kansas City, Missouri Water Services Department will construct 36,000' of water transmission piping from the East Bottoms Pump Station to Stadium Drive and I-435 to provide additional supply to Lee's Summit. Notification to Kansas City to begin the project was sent in January 2003.

Project Rationale:

Increases water supply from KC to Lee's Summit by 6 MGD to serve future customers.

Current Project Status:

The construction project was bid in the summer of 2004. This project is estimated to be completed by May 2010. The project has been delayed due to easement acqusitions. Kansas City has finally obtained the easement under the Neff rail yard. The contractor is planning to start work in January 2010. There still is an easement issue with one of the industries which should not affect work under the railroad tracks.


Lakeview / Madison Water Main Rehab

Last Updated

11/03/2009

Project Manager(s):

David Lohe
816-969-1814

Estimated Construction Dates:

-

Project Status

Future

Projected Funding:

$267,000

Project Description:

This project involves the construction of 1100 feet of a new 6-inch water main serving homes along Lakeview south of Third Street and along Madison south of Third Street. The new main will be located within the street right-of-way.

Project Rationale:

This project will replace existing mains that are in residents backyards. The existing mains have had numerous breaks.

Current Project Status:


Lakewood Way - Woods Chapel Rd. to Port Dr.

Last Updated

01/29/2010

Project Manager(s):

Bob Netterville
816-969-1813

Estimated Construction Dates:

Mar 01, 2010 - Oct 30, 2010

Project Status

In Design

Projected Funding:

$2,615,000

Project Description:

This project is completion of approximately 1/2- mile of Lakewood Way north of Woods Chapel Road. These segments complete the realignment of this road through the Eastport commercial development and adds a traffic signal at the intersection of Woods Chapel and Lakewood Way.

Project Rationale:

The realignment of the road provides increased separation between the Woods Chapel/I-470 interchange and the intersection of Lakewood Way and Woods Chapel in accordance with MoDOT standards. This separation will eliminate many of the traffic congestion problems occuring at the current intersection location.

Current Project Status:

The project is currently being designed by the in-house Public Works Engineering design team. Right-of-Way plans have been completed. Right-of-Way Tract Maps have been created and are in the hands of the R/W Agent to be forwarded to the appraiser. Completion of acquision is planned for late 2009 through early 2010. Review of the west end connection to the existing frontage road lead to the redesign of that pavement.Several pieces of R/W have been acquired at very reasonable rates.


Lee's Summit Road, Colbern Rd to city limits

Last Updated

01/29/2010

Project Manager(s):

George Binger
816-969-1828

Estimated Construction Dates:

-

Project Status

In Design

Projected Funding:

$8,657,000

Project Description:

This project is one of six projects funded by the 1/2 cent sales tax approved in 2007. Lee's Summit is participating on this project as a joint venture with Kansas City, MO and Jackson County. The project will consist of building a 3-lane road to address current traffic and safety needs. Right of way for future expansion to 5 lanes will be acquired to accommodate projected long-term traffic growth. The work will include sidewalks, multi-use path and utility relocation. Lee's Summit will manage design and construction from Colbern Road to Strother Road. Funding will be shared between Lee's Summit and Kansas City with each city paying for the portion within their city limits. Jackson County will oversee intersection improvements at Gregory Blvd. which is currently under construction. Kansas City, MO will design and build safety improvement between Strother Road and Gregory Blvd. Lee's Summit will provide funding for the portion of work within Lee's Summit. Design will begin from Colbern to Strother during the winter of 2009-10, with construction tentatively scheduled to start summer of 2013.

Project Rationale:

Primary purpose is safety improvements. Lee's Summit Road is heavily traveled minor arterial, but has several alignment and safety issues. This project will improve safety and expand capacity along this road.

Current Project Status:

The City of Lee's Summit is working with Kansas City, MO and Jackson County on this project. Jackson County is the lead coordinating agency for the entire corridor from Colbern Road to U.S. 40 Highway in Independence. The corridor concept study was completed in August 2007. Lee's Summit will manage design and construction for the section from Colbern Road to Strother Road. Lee's Summit and Kansas City are currently working on an intergovernmental agreement to initiate design along this portion of the road. Design is estimated to start in June 2010 after a design consultant is selected for the project.


Leeward and Sapello Drives Parallel Relief Sewer

Last Updated

11/16/2009

Project Manager(s):

Ray Seidelman
816-969-1851

Estimated Construction Dates:

Jul 08, 2009 - Oct 30, 2009

Project Status

In Construction

Projected Funding:

$532,000

Project Description:

The purpose of this project is to increase sanitary sewer capacity and reduce the potential for backups. Project design involves installing a new 12-inch sanitary sewer line along Sapelo Drive to provided increased capacity. The new line will work in parallel with the existing sanitary system. North of the new parallel line approximately 1180 lineal feet of existing sanitary line will be removed and replaced with larger pipe (713 ft of 12-inch pipe and 463 feet of 10-inch pipe). The alignment of replaced pipe will begin near 4224 Sapelo Drive and travel between the houses to Leeward drive, at 4116 Leeward Dr. the alignment turns north continues between the houses to connect to the manhole on the north side of Cole Younger Drive.

Project Rationale:

The existing sanitary system line is undersized. There have been numerous homeowner complaints of overflows in basements occurring in the project area.

Current Project Status:

The sewer main work is complete. Restoration is in progress.


Longview Blvd. Street Lighting

Last Updated

01/20/2010

Project Manager(s):

Jeff Wilke
816-969-1821

Estimated Construction Dates:

Mar 22, 2010 - Aug 20, 2010

Project Status

In Construction

Projected Funding:

$242,000

Project Description:

This project includes installation of a continuous street lighting system on Longview Blvd. from Longview Road to 3rd Street.

Project Rationale:

Lighting on arterial roadways is currently not part of the leased system. Safety is a concern for the driving public. Studies have shown that streets with continuous street lighting have a lower crash frequency at night than streets without lighting.

Current Project Status:

Construction will begin in March 2010.


Longview Road, Pryor Road to Ward Rd

Last Updated

11/30/2009

Project Manager(s):

David Wahl
816-969-1856

Estimated Construction Dates:

Oct 15, 2009 - Nov 15, 2010

Project Status

In Construction

Projected Funding:

$13,192,000

Project Description:

This project involves the construction of a collector road to replace the existing two-lane road from Sampson Road to Ward Road. The project includes a three-lane roadway, curbs and gutters, sidewalks, major drainage structures and streetlights. The total length is approximately 13,600 ft. The project includes the reconstruction of the bridge between Pryor and Murray as a four-lane structure. A traffic signal will be installed in a separate project at Longview Road and Ward Road. See the Ward Road & Longview Road Signal project for additional information.

Project Rationale:

This project is part of the 1997 Road Sales and Excise Tax program. As development in the area increases, Longview Road will become a major east-west corridor for the southwestern part of the City with connection to major north- south arterials, Longview Parkway and Ward Road. The existing bridge is only one-lane wide with a limited weight capacity.

Current Project Status:

This project is to be constructed in two phases. Phase I included the section of Longview Road from Sampson Road to Pryor Road. This Phase of the project is complete.

Phase II of this project includes the section of Longview Road from Pryor Road to Ward Road. The Project was bid on Aug 21, 2009. The conteract was awarded to Miles Excavating, Inc. and construction started the week of October 19, 2009. Construction is anticipated to be complete by November 2010.


M150 Water Relocation - Market to West City Limits

Last Updated

12/10/2009

Project Manager(s):

Ray Seidelman
816-969-1851

Estimated Construction Dates:

Sep 01, 2009 - Apr 01, 2010

Project Status

In Construction

Projected Funding:

$2,244,000

Project Description:

This water line project involves relocation of approximately 12,700 feet of water line due to the proposed MoDOT M150 Road Widening Project.  The project starts at Market Drive and ends at the emergency interconnect vault structure near the West City Limits. Approximately 3,700 feet of water line in existing easements from Market Drive to Regatta Drive will be relocated and replaced with 12-inch high density polyethylene (HDPE) pipe. From Regatta Drive to West City Limits, approximately 9,000 lineal feet of water line in right-of-way will be relocated and replaced with 12-inch HDPE pipe. The water line will connect with Kansas City Missouri's water main at the emergency interconnect vault.

Project Rationale:

The existing water line has a maintenance history of numerous repairs. Very corrosive soils have been observed along the project alignment. The larger water line is needed to provide adequate fire flows and water pressure in the area. The existing water main is located within the proposed M150 Road Widening Project.

Current Project Status:

All of the water main work on Lemans is complete. The contractor has been hampered by wet weather and cold teperatures.


Middle Big Creek - Mouse Creek Flow Holding Basin

Last Updated

11/03/2009

Project Manager(s):

Ray Seidelman
816-969-1851

Estimated Construction Dates:

Aug 01, 2009 - Aug 31, 2010

Project Status

In Construction

Projected Funding:

$6,213,000

Project Description:

This project is the design of an excess flow-holding basin, a pump station structure, a force main, and two (2) gravity sewer lines in the vicinity southwest of the intersection of Ward Road and M-150 Highway. The basin and sewer will serve existing and new development in the area including the Stoney Creek, Parkwood, Meadows of Summit Ridge and Arbor Walk subdivisions.

Project Rationale:

The basin is needed to handle peak wet weather flows that exceed the capacity of the existing Little Blue Valley Sewer District line under Raintree Lake.

Current Project Status:

The contractor has poured the footing and one half of the wall on the basket structure. The east west interceptor is complete. Tree removal has been completed behind the homes.The silt fence and security gate have been installed.


NW 1st and NW Whitlock Sewer Rehab

Last Updated

11/03/2009

Project Manager(s):

Ray Seidelman
816-969-1851

Estimated Construction Dates:

Sep 08, 2009 - Oct 15, 2009

Project Status

In Construction

Projected Funding:

$202,000

Project Description:

This project is the replacement of approximately 480 ft of existing 8-inch sewer to 10-inch concrete incased sanitary sewer line in the Sterling Hills subdivision. The existing line runs along the bottom of a rocky creek. Erosion and settlement problems have caused damage to the existing line and repairs are difficult due to poor access to the area. Replacement includes some relocation of the sanitary line and additional easements to improve access for the future.

Project Rationale:

The existing line is damaged. Emergency repairs have been required several times. Repair and maintenance work is difficult due to the line's location at the bottom of a relatively inaccessible ravine.

Current Project Status:

This project is complete.


Prairie Lee Lake Sewer System

Last Updated

11/03/2009

Project Manager(s):

Ray Seidelman
816-969-1851

Estimated Construction Dates:

-

Project Status

In Design

Projected Funding:

$954,000

Project Description:

Grinder pump system to serve the unsewered areas around Prairie Lee Lake. The City would construct approximately 18,000' of small diameter force main as the collection system. Prairie Lee Lake residents would construct the individual grinder pump systems, which include the service laterals. The City's portion of this project is funded by the Sewer Construction fund. However, the residents will need to establish an improvement district to maintain and operate the improvements.

Project Rationale:

This project serves existing residents by providing a collection system to replace privately-owned and maintained septic systems.

Current Project Status:

The engineer is finalizing the plans and specifications.


Pryor Rd Water - Longview Rd to Eagle View Drive D

Last Updated

11/03/2009

Project Manager(s):

Ray Seidelman
816-969-1851

Estimated Construction Dates:

-

Project Status

Future

Projected Funding:

$384,000

Project Description:

This project is the extension of a 16-inch water transmission main south from Scherer Road to connect to the existing 16-inch main at the north edge of the Eagle Creek subdivision. The City's cost will be the upsizing, or difference in costs between an 8-inch line installed by a developer and the 16-inch main that is needed for long term service. This project is also the extension of a 20-inch water transmission main south from Longview Road (connecting to an existing (proposed) 16-inch main at Longview Road) to Scherer Road. The schedule for this transmission main will depend on development (PRI property). The City's cost will be upsizing, or difference in costs between an 8-inch main installed by a developer and the 20-inch main.

Project Rationale:

This connection is needed to continue to provide adequate pressures and fire flows to development in the southwest part of the City.

Current Project Status:

This project will occur only when additional development along Pryor Road occurs, which will create the need to make the connection from the water line on Scherer to the end of the line near Eagle Creek subdivision.


Pryor Road, Scherer Road to Longview Road

Last Updated

01/26/2010

Project Manager(s):

Duke Wrisinger
816-969-1839

Estimated Construction Dates:

Mar 01, 2010 - Oct 01, 2010

Project Status

In Design

Projected Funding:

$3,989,000

Project Description:

This project involves the reconstruction of Pryor Road from Scherer Road to Longview Road. Though right-of-way for the ultimate improvements is acquired, only interim improvements are being constructed at this time. The ultimate improvements (expanding the road to a four-lane arterial) are unfunded. The schedule for those improvements will depend on future development in the area.

Project Rationale:

Pryor Road is a major north-south corridor in the western portion of the City. The projected increase in traffic in this area, due to commercial development at Hwy 50 & I-470 and the construction of an interchange at Pryor and I- 470, warrants the need for improvements.

Current Project Status:

Pryor Road Interim Improvements General comments: After removal of the old road, sight distances will be improved by flattening the hills and raising the valleys. While it will remain a two lane road, each lane will be widened to 12 feet and a 6 foot shoulder will be added. Turn lanes on Pryor will be added at each of the intersections. Storm water will continue to be carried alongside the road in open ditches and underneath the road in new box culverts. The interim improvements will not include any sidewalks, bike paths or traffic signals. In order to facilitate traffic coordination with the Longview Road Improvements, the work from Scherer to Longview should begin in the spring of 2010. Construction of the improvements will not allow traffic on Pryor, between Scherer and Longview. The Pryor and Scherer intersection will also be rebuilt, though those improvements can only be undertaken during school recess. Before construction starts, details about the schedule and the detour routes will be issued in a press release. The contractor has been chosen, and the construction contract is in the approval process. The pre-construction meeting will be held in February, and this information will be updated following that meeting.


Pryor Road/Blue Parkway and I-470 Interchange

Last Updated

07/28/2009

Project Manager(s):

Michael Park
816-969-1820

Estimated Construction Dates:

May 01, 2007 - Jun 01, 2010

Project Status

In Construction

Projected Funding:

$46,612,000

Project Description:

This project is the design and construction of two half- diamond interchanges on I- 470, one at Pryor Road and one at Blue Parkway, as well as collector-distributor roads between the two, over the existing I-470/US 50 interchange. The improvements at Pryor are required as part of the TIF agreement for the Summit Woods retail center, and are funded by the Summit Woods Transportation Development District (TDD). The remainder of the interchange project will be funded from a combination of TIF and state funds. MoDOT is managing the project.

Project Rationale:

Increased traffic associated with the retail center and the Summit Technology Campus severely impacts the function of the already overloaded I- 470/Hwy 50/Chipman interchange. The interchanges at Pryor and Blue Parkway will divert traffic away from the existing 470-50 interchange, alleviating some of the existing congestion.

Current Project Status:

The construction of Pryor Road interchange is complete. Blue Parkway interchange and connectors are under construction. Construction of Blue Parkway interchange and the connectors is expected to complete in June 2010, with Blue Parkway interchange open to traffic in the fall of 2009.


Raintree Lake Area - Water Main Rehab

Last Updated

11/03/2009

Project Manager(s):

Ray Seidelman
816-969-1851

Estimated Construction Dates:

Mar 23, 2009 - Sep 30, 2009

Project Status

In Construction

Projected Funding:

$1,476,000

Project Description:

This project includes either the replacement or rehabilitation of approximately 2,530 feet of deteriorated 4-inch and 6-inch water mains in several cul-de-sacs including Bowsprit Drive, Marline Drive, and Batten Drive. This project also includes either the rehabilitation or replacement of approximately 3,850 feet of 4-inch and 6-inch water mains on Harbor Circle, Lacrosse Court, Hidden Cove Drive, Hidden Cove Circle and Linden Lane. Plans include presenting a request in April, 2009 to the Public Works Committee and City Council to include Hidden Cove Court in the rehabilitation project. Temporary water mains are planned to supply customers with water service during construction.

Project Rationale:

This project will serve existing customers by replacement or rehabilitation of water mains that have had several breaks due to corrosion.

Current Project Status:

The project is completed.


Richardson, Balboa, Shamrock, John Knox Village

Last Updated

12/10/2009

Project Manager(s):

Ray Seidelman
816-969-1851

Estimated Construction Dates:

Jul 23, 2009 - Dec 30, 2009

Project Status

In Construction

Projected Funding:

$1,056,000

Project Description:

This project includes either the replacement or rehabilitation of approximately 1,500 feet of deteriorated 6-inch water main on Richardson Place between 5th Terrace and 7th Street, 1,100 feet of water main replacement or rehabilitation on Balboa Avenue between Chipman Road and Swann Road, 1,110 feet of water main replacement or rehabilitation on Shamrock Avenue between Obrien Road and Killarney Lane and the rehabilitation or replacement of approximately 1,770 feet of 6-inch water main on Peace Parkway between Moore Street and Shamrock Avenue in John Knox Village. Temporary water mains are planned to supply customers with water service during construction.

Project Rationale:

This project will serve existing customers by either replacement or rehabilitation of water mains that have had several breaks due to corrosion.

Current Project Status:

The project is complete.


Sampson Road Safety Improvment

Last Updated

01/29/2010

Project Manager(s):

George Binger
816-969-1828

Estimated Construction Dates:

Aug 01, 2010 - Sep 30, 2010

Project Status

In Design

Projected Funding:

$500,000

Project Description:

This project will straighten the S-curve located south of the bridge over Mouse Creek and north of Hook Road. The road will be widened to approximately 20-feet with shoulders. The length of road work will be about 500 feet. The road will be closed during construction.

Project Rationale:

This project is a safety improvement. The existing curve is blind, the road is very narrow and the ditches are very steep.

Current Project Status:

The project is currently in design. Design plans are about 65% complete, and the right of way plans are complete. The City has begun the process to acquire right of way for this work. Estimated construction start will be summer of 2010. Timing must be coordinated with closures along Scherer Road between Sampson and Pryor Roads to ensure effeicient access by emergency services.


Scruggs Rd Pump Station Excess Flow Holding Basin

Last Updated

11/03/2009

Project Manager(s):

David Lohe
816-969-1814

Estimated Construction Dates:

Sep 01, 2010 - May 15, 2011

Project Status

In Design

Projected Funding:

$1,262,000

Project Description:

This sanitary sewer improvement project consists of the expansion of the existing Excess Flow Holding Basin capacity from 1.4 MG to 4.9 MG.

Project Rationale:

This project will increase the wet weather capacity at the existing basin and reduce the potential of overflows due to future development in the watershed.

Current Project Status:

Construction for this project is expected to start in September 2010. It is the City's intention to have construction of the EFHB completed before spring of 2011.


SPL - Bristol and Lyon Relief Line

Last Updated

12/10/2009

Project Manager(s):

Ray Seidelman
816-969-1851

Estimated Construction Dates:

Jul 01, 2009 - Nov 23, 2009

Project Status

In Construction

Projected Funding:

$686,000

Project Description:

The purpose of this project is to increase sanitary sewer capacity and reduce the potential for backups. Also erosion and settlement problems have caused damage to the existing line and repairs are difficult due to poor access to the area. Project design involves replacement and upsizing of approximately 1610 ft of existing sanitary sewer line (104 lineal feet of 8-inch pipe and 1506 24-inch pipe) along the stream near the intersection of Bristol and Lyon Drives. In areas where the stream has previously eroded and damaged the sewer the new pipe will be incased in concrete, there is approximately 203 lineal feet of encased pipe planed in various locations along the alignment.

Project Rationale:

The existing sanitary system line is undersized and damaged. Emergency repairs have been required several times. Repair and maintenance work is difficult due to the line's location in the stream.

Current Project Status:

All of the sewer main is complete. There is some restoration work remaining.


SPL - Summit Mill Pump Station Relief Line

Last Updated

11/03/2009

Project Manager(s):

Ray Seidelman
816-969-1851

Estimated Construction Dates:

Aug 01, 2009 - Oct 12, 2009

Project Status

In Construction

Projected Funding:

$140,000

Project Description:

The purpose of this project is to increase sanitary sewer capacity and reduce the potential for backups. Project design involves replacement and upsizing the existing 8-inch sanitary line with 157 lineal feet of 15-inch sewer pipe. This project will eliminate use of the Summit Pump Station and it will be removed.

Project Rationale:

The existing sanitary system line is undersized. This area was identified using periodic reviews of maintenance records, staff knowledge of problem areas, customer complaints, and emergency repair calls.

Current Project Status:

This project is complete.


Strother Road Interchange

Last Updated

01/29/2010

Project Manager(s):

Bob Netterville
816-969-1813

Estimated Construction Dates:

Oct 01, 2008 - Oct 31, 2010

Project Status

In Construction

Projected Funding:

$33,700,000

Project Description:

This project involves the construction of an interchange at Strother Road and I- 470 Highway. A TDD/TIF has been approved for the Chapel Ridge development which will provide funding to design and construct the interchange and various adjacent roadway improvements. In addition to the TIF/TDD funding, $8 million of federal funding is available for construction.

Project Rationale:

As development continues in this area traffic demands will warrant an interchange between Colbern Road and Woods Chapel on I-470. This project will provide additional access to the Airport and developments west of I-470 and open up the property east of I-470 for future developments.

Current Project Status:

Strother Road Interchange on I-470 and Todd George Parkway from Colbern Rd. to Woods Chapel Rd. Construction began on Nov. 17, 2008 on the Strother Road Interchange. Bridges are open to traffic. The Todd George Parkway plans and specifications are now complete and under review & revision with input by MoDOT and the FHWA.


Sunderland Court - Water Main Rehab

Last Updated

11/03/2009

Project Manager(s):

Ray Seidelman
816-969-1851

Estimated Construction Dates:

Aug 15, 2009 - Sep 30, 2009

Project Status

In Construction

Projected Funding:

$185,000

Project Description:

This project includes either the replacement or rehabilitation of approximately 620 feet of deteriorated 6-inch water main on Sunderland Court. This project includes pipe bursting 478 feet of water main and open trench replacement of 137 feet of water main. Temporary water mains are planned to supply customers with water service during construction.

Project Rationale:

This project will serve existing customers by either the replacement or rehabilitation of water mains that have had several breaks due to corrosion.

Current Project Status:

The work is complete.


Ward Road and Longview Road Signal

Last Updated

07/28/2009

Project Manager(s):

Michael Park
816-969-1820

Estimated Construction Dates:

Jun 01, 2010 - Nov 30, 2010

Project Status

In Design

Projected Funding:

$904,000

Project Description:

This project includes installation of a traffic signal at the intersection of Ward Road and Longview Road, and construction of a southbound right turn and a northbound left turn on Ward. Improvements on Longview Road, including realignment with South Lea Drive will be part of the Longview Road project. Federal funding of $544,000 will be available for construction. The City's portion of the project will be funded from the Road & Bridge fund.

Project Rationale:

Traffic signal warrant study (1998) verified that existing traffic volumes warrant a traffic signal at this intersection.

Current Project Status:

Plans are approximately 95% complete and all right-of-way has been acquired. This project will be constructed around the same time as the completion of the east end of Longview Road Phase 2. A temporary traffic signal has been installed at the existing intersection to relieve congestion and improve safety until the permanent improvements are completed.


Ward Road and Persels Road Signal

Last Updated

12/01/2009

Project Manager(s):

John Barker
816-969-1850

Estimated Construction Dates:

May 01, 2011 - Oct 15, 2011

Project Status

In Design

Projected Funding:

$1,186,000

Project Description:

Installation of a traffic signal and geometric turn lanes at Ward Road and Persels Road. Currently, the east and west legs of Persels Road are offset due to the location of the inactive railroad tracks. In order to expedite the design and construction, the project will not utilize federal funding. Federal funding of $700,000 previously allocated for this project was transferred to the Lansgford Road project in FY2005.

Project Rationale:

A traffic study identified this intersection as warranting a traffic signal due to existing traffic volumes. Auxiliary turn lanes will facilitate turning movements and provide better progression through the intersection.

Current Project Status:

Design is approximately 90 percent complete. Right of way acquisition is completed. The project was on hold for about two years while the City considered whether to realign Persels Road and discussed with the Union Pacific RR options regarding the right-of-way. The City has decided not to realign Persels Road and has submitted permit applications for the work within the RR right-of-way.

The City has constructed a temporary signal for the intersection. The operation of the temporary signal requires that, after vehicles turn left from Persels onto Ward Rd, they must stop at the RED light on Ward Rd. The permanent signal is capable of being designed to eliminate that short RED.


Water Main Rehab - Independence Ave - Third

Last Updated

11/03/2009

Project Manager(s):

David Lohe
816-969-1814

Estimated Construction Dates:

-

Project Status

Future

Projected Funding:

$950,000

Project Description:

These projects involve the rehabilitation of 4,670 feet of 6-inch and 8-inch water mains located along Independence Avenue between 3rd Street and Swann Road, and the rehabilitation of 600 feet of 4-inch and 1,040 feet of 6-inch water main on 3rd Street from Grand Avenue to Summit Avenue.

Project Rationale:

This project will serve existing customers by either replacement or rehabilitation of the water main that has had several breaks due to corrosion. There have been six breaks on the Third Street water main recently reported.

Current Project Status:

2012 Construction


Water Main Rehab - Village Fair

Last Updated

11/03/2009

Project Manager(s):

David Lohe
816-969-1814

Estimated Construction Dates:

Mar 01, 2011 - Aug 01, 2011

Project Status

Future

Projected Funding:

$968,000

Project Description:

This project includes rehabilitation of approximately 8,187 feet of water line in the Village Fair subdivision. Existing 6-inch water lines running along Village Drive, Ward Road, Carroll Drive and Fair Lane will be replaced. Half of the line on Kay Drive, from the intersection of Carroll Dr. and Kay Dr. to the fire hydrant, will also be replaced. The existing 4-inch water line running along Falk Drive will be upsized to a 6-inch water line. This project will be coordinated with the Village Fair Sewer Rehabilitation Project.

Project Rationale:

The existing lines have a history of numerous repairs.

Current Project Status:


Woods Chapel Road Street Lighting

Last Updated

01/20/2010

Project Manager(s):

Jeff Wilke
816-969-1821

Estimated Construction Dates:

Mar 22, 2010 - Jul 21, 2010

Project Status

In Construction

Projected Funding:

$256,000

Project Description:

This project includes the installation of a continuous street lighting system on Woods Chapel Road from Independence Avenue to I-470.

Project Rationale:

Lighting on arterial roadways is currently not part of the leased system. Safety is a concern for the driving public. Studies have shown that streets with continuous street lighting have a lower crash frequency at night than streets without lighting.

Current Project Status:

Construction will begin in March 2010.


Woods Chapel, I-470 to Liggett.

Last Updated

01/29/2010

Project Manager(s):

Mike Anderson
816-969-1817

Estimated Construction Dates:

Mar 30, 2008 - Nov 01, 2009

Project Status

In Construction

Projected Funding:

$5,396,000

Project Description:

This is a joint project between Jackson County and the City of Lee's Summit that involves the realignment and construction of Woods Chapel from I-470 east to Liggett Road. The project includes construction of a four-lane arterial roadway, curb and gutters, sidewalks and drainage structures. The overall project is 7,200 feet in length and should be completed in the Fall of 2009. Jackson County is the lead agency for this project.

Project Rationale:

This project is part of the 1997 Road Sales and Excise Tax program. Woods Chapel Road serves as a major route through Lee's Summit that extends from Lee's Summit Road to US 40 Highway, adjacent to Lake Jacomo. The existing two-lane road is narrow, winding, deteriorating and is nearing it's capacity to handle traffic.

Current Project Status:

For the most current information and photo's of the project, Follow the link below the the Jackson County Web Page...


WPL - Thames and Victoria Relief Line

Last Updated

11/03/2009

Project Manager(s):

Ray Seidelman
816-969-1851

Estimated Construction Dates:

Feb 24, 2009 - Oct 15, 2009

Project Status

In Construction

Projected Funding:

$630,000

Project Description:

The purpose of this project is to increase sanitary sewer capacity and reduce the potential for backups. Project design involves removing and replacing the existing 8-inch sanitary line with 1830 linear feet of 15-inch sanitary pipe to increase capacity of the system. There is also 330 linear feet of 8-inch sewer line in this area that will be replaced.

Project Rationale:

The existing sanitary system line is undersized. This area was identified using periodic reviews of maintenance records, staff knowledge of problem areas, customer complaints, and emergency repair calls.

Current Project Status:

This prject is complete


WPL Watershed - Todd George Rd Pump Station

Last Updated

09/21/2009

Project Manager(s):

David Lohe
816-969-1814

Estimated Construction Dates:

Mar 01, 2011 - Aug 01, 2011

Project Status

Future

Projected Funding:

$249,000

Project Description:

This sanitary sewer improvement project consists of the Todd George wet weather pump station to serve a residential area north of the Tudor Road Pump Station.

Project Rationale:

This project maximizes the use of the Tudor Road Pump Station EFHB (1.0 MG) and reduces the risk of sanitary sewer overflows and backups in the Mist subdivision.

Current Project Status: