Directions:

Obtain project details by selecting the desired project on the map, or review a list of unmapped projects from the link above.


Lee's Summit, MO

2010 Bond Curb Replacement

Last Updated

05/23/2013

Project Manager(s):

George Binger
816-969-1800

Estimated Construction Dates:

May 28, 2013 - Oct 31, 2013

Project Status

In Construction

Projected Funding:

$9,360,000

Project Description:

The project was approved by voters as part of the November 2010 "No Tax Increase" bond election. The funding was scheduled to replace approximately 400,000 feet of curbs throughout the City.

Project Rationale:

City staff has identified approximately 2,000,000 feet of deteriorating curb and gutter throughout the community that needs to be replaced. The annual funding available for curb replacement on roads included in the overlay program is not adequate to address this backlog. The funding approved by voters is anticipated to address about 20% of the needed replacement and will focus on the worst areas.

Current Project Status:

Three construction phases in 2011 and 2012 replaced 415,000 linear feet of curb. That exceeded the 400,000 feet estimated in the bond issue. The curb replacement work was completed in time to meet the schedule originally proposed for the bond issue work. The City was able to replace more curb because of relatively low bid prices received for all three phases of work. Money is still left in the budget to replace additional curb that warrants replacement. City Staff is currently working to issue construction bids for an additional construction work to start in summer 2013. This work is estimated to replace an additional 80,000 to 100,000 linear feet of curb based on prices. The total curb replaced by the bond issue funding will be approximately 500,000 feet of curb. This which is 25% over the bond issue goal. More information on the rating system used to prioritize the work and locations currently included in the program is available on the City's website at the link shown below.


Airport Land Acquisition

Last Updated

10/31/2012

Project Manager(s):

John Barker
816-969-1800

Estimated Construction Dates:

Jun 01, 2005 - Apr 30, 2013

Project Status

N/A

Projected Funding:

$18,200,000

Project Description:

This project involves the purchase of properties adjacent to the Lee's Summit Municipal Airport as shown on the Airport Layout Plan approved in March 2000.

Project Rationale:

This land acquisition is required in order to provide Runway Protection Zones RPZ's)for the extension of Runway 18/36; to provide RPZ's for both ends of Runway 11-29; and to provide development area for the construction of a new terminal and new hangars to replace the existing hangars that will be demolished to meet FAA airport design standards.

Current Project Status:

The process of land acquisition includes surveys, appraisals, Environmental Site Assessments, and negotiations. The process is underway for all of the properties involved. The City has acquired fourteen of the tracts.

The surveyor and appraiser have completed all of the surveys and appraisals for the remaining tracts.

The land acquisition program for the airport was on hold pending the outcome of the Airport Business Plan and the CIP Implementation Plan. The Airport Business Plan has been formally adopted by City Council. Land Acquisition resumed in the summer of 2011.


Arbores Pump Station

Last Updated

03/15/2012

Project Manager(s):

Kevin York
816-969-1800

Estimated Construction Dates:

Mar 04, 2013 - Aug 30, 2013

Project Status

In Design

Projected Funding:

$459,000

Project Description:

This project involves repair of the Arbores Pump Station and installation of approximately 2,000 feet of sanitary sewer line.

Project Rationale:

The pump station is 25 years old and requires repair. The existing force main needs to be replaced so a new sewer line is planned to be installed.

Current Project Status:

This project has been combined with WPL Watershed - Todd George Rd Pump Station, Westview School Sanitary Sewer Bank Stabilization and Lee's Summit Road Lift Station EFHB.


Bailey Road, Route 291 to Hamblen Rd

Last Updated

02/20/2013

Project Manager(s):

Scott Ward
816-969-1800

Estimated Construction Dates:

Apr 01, 2013 - Aug 31, 2014

Project Status

In Design

Projected Funding:

$8,389,000

Project Description:

This project is one of six in the Lee's Summit Thoroughfare Master Plan. Funding for this project comes from the extension of the 1/2 cent sales tax (for Transportation Improvements) passed by voters in the spring of 2007. The project will construct a new roadway from M-291 east to the intersection of Hamblen Road and Bailey Road. A significant part of the project will be the design and construction of a bridge over the Union Pacific Railroad.

Project Rationale:

Current Project Status:

The construction of Phase 2 is expected to start in early April. The project is advertised and bids will be opened on February 21st. Once the contract is awarded then hard dates for commencement of the work will be determined.


Bayview Drive Water- Channel Dr to Shore Line Dr

Last Updated

03/15/2012

Project Manager(s):

Kevin York
816-969-1800

Estimated Construction Dates:

Apr 30, 2012 - Nov 29, 2013

Project Status

In Design

Projected Funding:

$656,000

Project Description:

Relocation of approximately 2,300 linear feet of 6-inch and 8-inch water mains and service connections along Bayview Drive from Channel Dr to Shore Line Drive. Plans include relocating the line along the existing roadway due to the numerous obstructions along the existing alignment.

Project Rationale:

The existing line is deep and located under retaining walls, sidewalks and landscaping features, which results in high maintenance costs when repairs are needed. The main has experienced several breaks.

Current Project Status:

This project was scheduled for construction during the summer of 2011. This project has since been combined with the Water Main Rehab-FY 2011 and the Water Main Rehab-FY 2012 projects. The estimated construction schedule includes the combination of all three projects in the 2011-2015 Capital Improvement Program for Water Utilities projects. Estimated start and completion dates will vary between each project location as work proceeds.


Blackwell Interchange at 50 HWY

Last Updated

08/20/2012

Project Manager(s):

Michael Park
816-969-1800

Estimated Construction Dates:

Apr 01, 2014 -

Project Status

In Design

Projected Funding:

$23,000,000

Project Description:

Extension of Blackwell Road across 50 Highway, having a diamond interchange. Construction of Blue Parkway to Blackwell Road and Oldham Parkway to Smart Road, with an intersection at Blackwell Road. This project will be fully funded by the East 50 HWY TIF and managed by the City of Lee's Summit. MoDOT, City of Lake Lottawanna and Jackson County are supporting agencies with property interests and/or ownership.

Project Rationale:

Traffic conditions at the interchange of Todd George Parkway and 50 Highway will not accomodate the immediate and projected growth of surrounding development. Improvements to Todd George Parkway interchange are planned, but cannot mitigate the traffic congestion without alternate access to 50 Highway in eastern Lee's Summit. Blackwell interchange has been planned for over 40 years. Blackwell interchange will relieve some of the congestion at Todd George Parkway and surrounding streets, provide better access to eastern Lee's Summit, minimize the impact of travel during construction at Todd George Interchange, encourage economic development in the newly annexed property and meet the City's long range traffic demand.

Current Project Status:

Design is approximately 98% complete. The interchange has been designed with roundabout traffic control where the ramps intersect with Blackwell Road and at the intersection of Blackwell Road and Blue Parkway/Shenandoah Drive. All permits and enviornmental clearances have been approved. Acquisition of right-of-way, utility relocation and construction will be deferred until TIF funds are available to cover associated project costs. Such funding is contingent on development activity within the TIF Area. TIF Funding may be supplemented by State Cost Share Program. The State has awarded Cost Share Funding at 50%, pending City Council agreement.


CC Watershed - CC-16, CC- 20 Private I/I Rehab

Last Updated

08/12/2011

Project Manager(s):

Kevin York
816-969-1800

Estimated Construction Dates:

Oct 01, 2010 -

Project Status

In Construction

Projected Funding:

$584,000

Project Description:

This sanitary sewer improvement project consists of completing the private I/I rehabiliation work identified in the Sewer System Evaluation Survey(SSES) in the identified sub-watersheds CC-16 and CC-20. These improvements consist of removal of ground water infiltration and inflow from home drain systems.

Project Rationale:

This project will serve existing customers by reducing I/I from these sources which will alleviate sanitary sewer overflows and backups in homes.

Current Project Status:


CC Watershed - CC-17, CC- 21 Private I/I Rehab

Last Updated

08/12/2011

Project Manager(s):

David Lohe
816-969-1800

Estimated Construction Dates:

Jul 01, 2014 - Jul 01, 2016

Project Status

Future

Projected Funding:

$1,959,000

Project Description:

This sanitary sewer improvement project consists of completing the private I/I rehabiliation work identified in the Sewer System Evaluation Survey (SSES) in the identified sub-watersheds CC-17 and CC-21. These improvements consist of removal of ground water infiltration and inflow from home drain systems.

Project Rationale:

This project will serve existing customers by reducing I/I from these sources which will alleviate sanitary sewer overflows and backups in homes.

Current Project Status:


Cedar Creek Interceptor Improvements 2-2

Last Updated

09/10/2012

Project Manager(s):

David Lohe
816-969-1800

Estimated Construction Dates:

Sep 10, 2013 - Aug 25, 2014

Project Status

In Design

Projected Funding:

$2,645,000

Project Description:

This sanitary sewer improvement project consists of the construction of approximately 9300 LF of sanitary sewer lines ranging in pipe size from 36-inches to 48-inches in diameter on the upper segments of Cedar Creek interceptor.

Project Rationale:

The existing sanitary sewer lines do not have capacity to convey the predicted wet-weather flows nor meet the future needs of development in the watershed. A federal grant was obtained through economic development contacts which will pay for just over half of the cost of the project.

Current Project Status:


Cedar Creek Trunk-Winterset Woods & Sterling Hills

Last Updated

08/12/2011

Project Manager(s):

David Lohe
816-969-1800

Estimated Construction Dates:

Feb 01, 2014 - Aug 01, 2014

Project Status

Future

Projected Funding:

$565,000

Project Description:

This sanitary sewer improvement project consists of the construction of 2,600 LF of sanitary sewer relief lines ranging in pipe size from 12-inches to 15-inches in diameter on the lower segments of the Cedar Creek Interceptor Subbasins CC-03 and CC-04.

Project Rationale:

The existing lines do not have capacity to convey the predicted peak wet weather sanitary sewer flows nor meet the future needs of development. The condition of the existing pipe system is also a concern. There has been at least one documented overflow in these subbasins.

Current Project Status:


Chipman Road, View High Dr to Bent Tree Dr

Last Updated

01/16/2013

Project Manager(s):

John Barker
816-969-1800

Estimated Construction Dates:

Apr 01, 2014 - Jun 30, 2015

Project Status

Future

Projected Funding:

$10,414,000

Project Description:

This project is one of six projects funded by the 2007 1/2 cent sales tax renewal. This project will reconstruct the roadway as a 3-lane facility and acquire right-of-way for ultimate divided 4-lane facility with turn lanes. The existing one-lane RR tunnel will be removed, and widened to support two-way traffic. The project will not be constructed until the Union Pacific right-of-way is acquired by the city.

Project Rationale:

SAFETY: This project will improve safety by leveling the roadway and improving sight distance. The right of way component will preserve right of way for future capacity improvements.

Current Project Status:

Wilson and Company of Kansas City, MO began the conceptual study, design and survey work in July 2010. The Concept Phase studied the costs and impacts of several horizontal and vertical alignments. The Concept Phase Alignment report and Traffic Study were completed in January 2011. A public meeting was held on February 8, 2011 and the alignment options that were investigated were presented as well as the recommended alignment. The preliminary design began in May, 2011. Wilson completed preliminary design in October, 2011 and and completed the right-of-way plans, tract maps and legal descriptions in early 2012. Land acquisition for easements and right-of-way is on hold until the railroad right-of-way issue is resolved. Plans are 90% completed. The 90% Marking and Signing Plans are included below.


Earthwork for Runway 18-36 Extension and Parallel

Last Updated

10/31/2012

Project Manager(s):

John Barker
816-969-1800

Estimated Construction Dates:

Aug 30, 2013 - Nov 01, 2014

Project Status

Annual Program

Projected Funding:

$8,317,000,000

Project Description:

In accordance with the City Council adopted Airport Business Plan, this project includes the earthwork for the 100 foot wide extension of the existing Runway 18-36 from 4,014 feet to 5,300 feet and for the extension of the west parallel taxiway.

Project Rationale:

Extension of the runway will allow operations of a greater variety of business class aircraft under a greater range of weather conditions. This project will serve to improve the airport and allow more corporate jets to use the facility. These improvements should increase the economic value of the airport to the city. In addition the existing west parallel taxiway is located at 225 feet from Runway 18-36, which is less than the standard separation for a Class C airport. The taxiway is to be relocated to 400 feet from Runway 18-36, which meets the Class C standard.

Current Project Status:

Crawford, Murphy and Tilly (CMT) began the design in May, 2011. Application for environmental permits have been submitted. The design is approximately 80% copmplete and construction can begin in fall 2013 if land acquisition is complete and the FAA Grants are in place to fund the project.


Hook Road: Ward Rd to Route 291

Last Updated

12/03/2012

Project Manager(s):

Bob Netterville
816-969-1800

Estimated Construction Dates:

Feb 01, 2014 - Nov 01, 2014

Project Status

In Design

Projected Funding:

$7,908,000

Project Description:

This project will widen and reconstruct Hook Road from Ward Road to Hwy. 291. Proposed improvements are to each lane to 12 feet, add paved shoulders and improve drainage pipes/culverts under the road.

Project Rationale:

This project is one of six projects funded by the 2007 1/2 cent sales tax.

Current Project Status:

Project design is nearly completed. The work has been performed by in-house by City staff. The land survey has been completed. The work on design is nearing the Final mile-stone. Right of way acquistion will take place in early 2013. O&E and easement legal discriptions have been written.


Jefferson Street Water - Market to Stuart Road

Last Updated

08/15/2011

Project Manager(s):

David Lohe
816-969-1800

Estimated Construction Dates:

-

Project Status

Future

Project Description:

This rehabilitation project includes the replacement of existing 2-inch galvanized and 4-inch cast-iron water lines with new 8-inch diameter ductile iron lines along Jefferson. The project is funded by the Water Construction fund.

Project Rationale:

The existing lines have a long maintenance history of numerous repairs.

Current Project Status:

This is a future project.


Jefferson Street, Stuart Rd to Persels Rd

Last Updated

04/24/2013

Project Manager(s):

Shannon Jeffries
816-969-1800

Estimated Construction Dates:

Apr 01, 2014 - Jul 01, 2015

Project Status

In Design

Projected Funding:

$9,714,000

Project Description:

Widen and reconstruct Jefferson Street as a three-lane road from Scherer to Persels. The road will be two lanes from Stuart to Scherer.

Project Rationale:

This project is one of six projects funded by the 1/2 cent sales tax, approved in 2007. Main purpose is to improve safety and flow of traffic along this road.

Current Project Status:

Burns and McDonnell is the design consultant for this project. The project is currently in the design phase which is expected to continue through late 2013. Right of way acquistion is expected to occur in mid-2013. Construction is expected to occur in 2014-2015. A public meeting was held Tuesday, April 23rd. Documents from that meeting are posted on this page.


KC Water Supply Proposal - Phase III

Last Updated

08/15/2011

Project Manager(s):

Ray Seidelman
816-969-1800

Estimated Construction Dates:

-

Project Status

In Construction

Projected Funding:

$7,867,000

Project Description:

Kansas City, Missouri Water Services Department will construct 36,000' of water transmission piping from the East Bottoms Pump Station to Stadium Drive and I-435 to provide additional supply to Lee's Summit. Notification to Kansas City to begin the project was sent in January 2003.

Project Rationale:

Increases water supply from KC to Lee's Summit by 6 MGD to serve future customers.

Current Project Status:

The contractor has started to work on the remaining main.


Lee's Summit Road Lift Station EFHB

Last Updated

03/15/2012

Project Manager(s):

Kevin York
816-969-1800

Estimated Construction Dates:

Mar 04, 2013 - Aug 30, 2013

Project Status

In Design

Projected Funding:

$150,000

Project Description:

This project involves rehabilitation of the excess flow holding basin at the Lee's Summit Road Lift Station. The initial project will be a study to recommend appropriate rehab measures. The project budget will be finalized once the study is complete.

Project Rationale:

The concrete-lined basin leaks and fills with groundwater, representing a source of I&I into the sanitary sewer system.

Current Project Status:

This project has been combined with WPL Watershed - Todd George Rd Pump Station, Westview School Sanitary Sewer Bank Stabilization and Arbores Pump Station.


Lee's Summit Road, Colbern Rd to city limits

Last Updated

03/05/2013

Project Manager(s):

George Binger
816-969-1800

Estimated Construction Dates:

Jun 30, 2014 - Jun 30, 2016

Project Status

In Design

Projected Funding:

$16,273,000

Project Description:

This project is one of six projects funded by the 1/2 cent sales tax approved in 2007. Lee's Summit is participating on this project as a joint venture with Kansas City, MO and Jackson County. The project will consist of building a 3-lane road with turn lanes. The work will include paved shoulders, multi-use path, street lighting and utility relocation. Lee's Summit will manage design and construction from Colbern Road to Gregory Boulevard. Funding will be shared between Lee's Summit and Kansas City with each city paying for the portion within their city limits. There has also been federal funding allocated for this project.

Project Rationale:

Primary purpose is safety improvements. Lee's Summit Road is heavily traveled minor arterial, but has several alignment and safety issues. This project will improve safety and expand capacity along this road.

Current Project Status:

Preliminary design work has been completed and Right of Way Plans are almost complete. The City expects receive approval to start the right of way acquisition process in April of this year. The process first begins with obtaining appraisals, reviewing the appraisals and then making initial contact with property owners. Property owners will be contact starting in the summer of 2013. The initial environmental survey has been completed, and the project has been cleared for environmental approval to meet the National Environmental Policy Act requirements. The January 29th, 2013 public meeting provided information regarding the preliminary plans. The boards shown at the meeting have been linked to this page. The boards show the roadway configurations, proposed construction phasing and estimated schedule information. Designers are currently working on right of way plans and final design plans. Right of way acquisition is planned to start in spring 2013 and extend through spring 2014. Construction should start in summer 2014 and be completed in 2016.


North Prairie Lee Lake Sewer System

Last Updated

01/09/2012

Project Manager(s):

David Wahl
816-969-1800

Estimated Construction Dates:

Oct 24, 2011 - Apr 30, 2012

Project Status

In Construction

Projected Funding:

$406,000

Project Description:

This project involves a low pressure sewer system to serve unsewered areas around Prairie Lee Lake as a collaborative project with the residents of this community. The north phase of the project consists of approximately 4,600 feet of small diameter forcemain as the collection system. The residents served by the system will need to establish an improvement district to fund, maintain, and operate the improvements.

Project Rationale:

This project serves existing residents by providing a collection system to replace privately-owned and maintained septic systems.

Current Project Status:

The plans and specifications were revised and combined with the South Prairie Lee Lake Sewer System. Please refer to the South Prairie Lee Lake Sewer System for progress updates.


Scruggs Rd Pump Station Excess Flow Holding Basin

Last Updated

09/10/2012

Project Manager(s):

David Lohe
816-969-1800

Estimated Construction Dates:

Jun 11, 2013 - Dec 07, 2013

Project Status

In Design

Projected Funding:

$1,262,000

Project Description:

This sanitary sewer improvement project consists of the expansion of the existing Excess Flow Holding Basin capacity from 1.4 MG to 4.9 MG.

Project Rationale:

This project will increase the wet weather capacity at the existing basin and reduce the potential of overflows due to future development in the watershed.

Current Project Status:


South Prairie Lee Lake Sewer System

Last Updated

07/13/2012

Project Manager(s):

David Wahl
816-969-1800

Estimated Construction Dates:

Oct 24, 2011 - Apr 30, 2012

Project Status

In Construction

Projected Funding:

$548,000

Project Description:

This project involves a low pressure sewer system to serve unsewered areas around Prairie Lee Lake as a collaborative project with the residents of this community. The south phase of the project consists of approximately 7,700 feet of small diameter forcemain as the collection system.

Project Rationale:

This project serves existing residents by providing a collection system to replace privately-owned and maintained septic systems.

Current Project Status:

The project has been re-combined with the the North system. The plans and specifications for the combined project have been approved by MDNR. The construction contract has been awarded. Construction started in November, beginning on south of Prairie Lee Lake. The system is installed and is now ready for residential connection. Some construction activity will remain including restoration of excavated areas (seed or sod) and revised Odor Control Station configuration and relocation of the south Odor Control Station.


Strother Road: Lee's Summit Road to Independence A

Last Updated

07/10/2012

Project Manager(s):

Shannon Jeffries
816-969-1800

Estimated Construction Dates:

Mar 01, 2013 - Apr 30, 2014

Project Status

In Design

Projected Funding:

$3,675,000

Project Description:

The project includes reconstruction of Strother Road from Lee's Summit Road to Independence Avenue on a new alignment just to the north of the existing road. The road will have a two lanes with paved shoulders.

Project Rationale:

Currently, Strother Road is narrow and substandard in its construction. The proposed reconstruction was identified in the 2006 Thoroughfare Master Plan. The project was approved by voters in the 2010 bond election.

Current Project Status:

City staff is currently working through the preliminary design phase of this project and right-of-way acquisition.


Tudor Road Improvements

Last Updated

09/07/2012

Project Manager(s):

Scott Ward
816-969-1800

Estimated Construction Dates:

Mar 04, 2013 - Nov 04, 2013

Project Status

In Design

Projected Funding:

$11,000

Project Description:

The Tudor Road Improvements project will complete the connection between NW Road Ward and NE Douglas Street. The proposed road will be a divided four lane, built to arterial standards, and have street lights, a sidewalk and a multi-use path. A major component of the project is a bridge over the Union Pacific Railroad. Due to the time required to have the Union Pacific review and approve the bridge over their tracks, the project will be built in two phases. Phase one, from Main to Douglas, is expected to be under construction this fall and completed by winter. Phase two will commence construction upon completion of the agreement with the Union Pacific Railroad, and work on phase two is estimated to begin in the spring of 2012. Depending on construction costs, additional work could include turn lane improvements to the high school and a left turn lane onto NE Woodbury Lane.

Project Rationale:

The Tudor Road Improvements project was approved by voters during the November 2010 no tax increase general obligation bond election. This project will provide another arterial link between Ward Road and Douglas Street and open up approximately 190 acres to development.

Current Project Status:

This project has been divided into two phases; the Phase 1 improvements are from Douglas to Main, and Phase 2 is from Main to Ward. The construction schedule reflects the Phase 1 improvements, and this schedule is dependent on property acquisition. It is anticipated the property for the improvements will be acquired this fall. Phase 2 (Main to Ward) is under design and is approximately 50% complete. Phase 2 includes the bridge over the Union Pacific Railroad's main line and will require agreements with the railroad. Also phase 2 includes significant utility relocations and property acquisition.


Westview School Sanitary Sewer Bank Stabilization

Last Updated

03/15/2012

Project Manager(s):

Kevin York
816-969-1800

Estimated Construction Dates:

Mar 04, 2013 - Aug 30, 2013

Project Status

In Design

Projected Funding:

$160,000

Project Description:

This project involves the re-routing of sanitary sewer lines and to abandon approximately 800 lf of main in the stream bank.

Project Rationale:

The re-routing is needed to eliminate erosion along a sewer line that is in service.

Current Project Status:

This project has been combined with WPL Watershed - Todd George Rd Pump Station, Arbores Pump Station and Lee's Summit Road Lift Station EFHB.


WPL Watershed - Todd George Rd Pump Station

Last Updated

03/15/2012

Project Manager(s):

Kevin York
816-969-1800

Estimated Construction Dates:

Mar 04, 2013 - Nov 09, 2013

Project Status

In Design

Projected Funding:

$249,000

Project Description:

This sanitary sewer improvement project consists of the Todd George wet weather pump station to serve a residential area north of the Tudor Road Pump Station.

Project Rationale:

This project maximizes the use of the Tudor Road Pump Station EFHB (1.0 MG) and reduces the risk of sanitary sewer overflows and backups in the Mist subdivision.

Current Project Status:

This project has been combined with Westview School Sanitary Sewer Bank Stabilization, Arbores Pump Station and Lee's Summit Road Lift Station EFHB.