Directions:

Obtain project details by selecting the desired project on the map, or review a list of unmapped projects from the link above.


Lee's Summit, MO

Airport Land Acquisition

Last Updated

08/18/2009

Project Manager(s):

John Barker
816-969-1850

Estimated Construction Dates:

Jun 01, 2005 - Jun 30, 2010

Project Status

N/A

Projected Funding:

$18,200,000

Project Description:

This project involves the purchase of properties adjacent to the Lee's Summit Municipal Airport as shown on the Airport Layout Plan approved in March 2000.

Project Rationale:

This land acquisition is required in order to provide Runway Protection Zones RPZ's)for the extension of Runway 18/36; to provide RPZ's for both ends of Runway 11-29; and to provide development area for the construction of a new terminal and new hangars to replace the existing hangars that will be demolished to meet FAA airport design standards.

Current Project Status:

The process of land acquisition includes surveys, appraisals, Environmental Site Assessments, and negotiations. The process is underway for all of the properties involved. The City has acquired thirteen of the tracts and has one offer pending.

The surveyor and appraiser have completed all of the surveys and appraisals for the remaining tracts.

The land acquisition program for the airport is on hold pending the outcome of the Airport Business Plan.


Airport Preliminary Engineering

Last Updated

08/18/2009

Project Manager(s):

John Barker
816-969-1850

Estimated Construction Dates:

Apr 01, 2004 - Sep 30, 2007

Project Status

N/A

Projected Funding:

$577,000

Project Description:

This project includes thirty percent engineering design, drawings, and estimates for the development of the airport as depicted in the Master Plan adopted in March, 2000.

Project Rationale:

This project is needed in order to provide engineered design and estimates to verify previous cost estimates.

Current Project Status:

Crawford Murphy and Tilley is the consultant and has submitted the drawings and report to finalize the 30 percent engineering.


East Terminal Area - LXT

Last Updated

03/22/2010

Project Manager(s):

John Barker
816-969-1850

Estimated Construction Dates:

Jun 03, 2008 - Jun 01, 2010

Project Status

In Construction

Projected Funding:

$6,500,000

Project Description:

This Project began on June 3, 2008. The project consisted of the development of a new parallel taxiway on the East side of the Airport and an aircraft parking apron area. Also included were installation of wildlife fencing, clearing of obstructions in the runway protection area, and the remarking of both runways. The work was performed by Emery Sapp & Sons.

Project Rationale:

The Masterplan for the airport includes upgrading the airport to a C-II airport. The west parallel taxiway is too close to the north-south runway (R/W 18-36) to meet the C-II standards. A new terminal area needs to be developed on the east side of R/W 18-36 before the existing terminal and some hangars can be removed, allowing the relocation of the west parallel taxiway.

Current Project Status:

With the exception of final seeding in some areas, this project is complete. Seeding will be performed within the specified dates for seeding in the spring of 2010.